Beverly Avenue Project

Beverly Ave Project - Phase 3A

Project Update - July 16, 2019

Crews are continuing to work between 4th and 5th Street in Alley D but cars are being let through as needed. This crew is grading the road and preparing for pavement.

A crew is working along 4th Street preparing for sidewalks and curbs. 4th Street remains open.

Coastal Drilling is still working in the same area between 417 and 418 off of Beverly Avenue to the South drilling and setting piles for a retaining wall.

Infinity Electric is working along Beverly Avenue installing conduit for street lighting from 3rd to 5th Street. They should only be working in the sidewalk areas so this will not affect vehicular traffic.

We will provide additional updates as available. Please check back often for updates or sign up for our alert notifications on the top right of this page.

Overview

Beginning March 11, construction will begin on Beverly Avenue and Beverly Alleyway. The expected substantial completion date for this phase of the project is August 9. These dates are dependent on weather and unforseen conditions. As the construction begins, we will try to reduce the impact to residents in the area; however, parking and traffic will be affected. We will update this page frequently with project information including parking and road closures. You can also sign-up by clicking the Beverly Ave Project Alerts title on the right to receive text and email notifications about upcoming parking restrictions, traffic restrictions (i.e. possible changes to one-direction traffic), pedestrian detours and full road closures.

This construction project includes Beverly Avenue, 4th Street, Beverly Alleyway, and the 5th Street Right-of-way between 3rd Street and 6th Street. This streetscape project includes widening and repaving of the roadway, stormwater upgrades, sidewalks and ADA curb ramps, lighting, retaining walls, and dumpster enclosures.

Timeline

  • Pre-Construction Meeting with Contractor, Designer, Utility Companies, and city staff – March 1
  • Construction begins – March 11*
  • WVU Last Day of Class – April 26
  • WVU Graduation – May 10, 11, 12
  • Project Substantial Complete – August 9**
  • First Day of WVU Class – August 21
  • Final Project Acceptance – September 26**

*Dependent on award paperwork finalization
**Dependent on weather and unforeseen conditions

  1. On street parking restricted on Beverly Alley July 8-12

    Parking will be closed on Beverly Alley between 433 Beverly Avenue and 311 4th Street Monday, July 8 to Friday, July 12 from 7:00 am – 5:00 pm. Construction crews will be grading the alley in preparation for pavement. Read On...
  2. Portion of Beverly Ave. closed July 8-12

    Beverly Avenue will be closed to through traffic between 331 Beverly Avenue and 311 Beverly Avenue Monday, July 8 to Friday, July 12 from 7:00 a.m. to 5:00 p.m. for the installation of a storm sewer. Read On...
  3. Portion of Beverly Ave. closed beginning Monday, July 8

    Construction will take place between 417 Beverly Avenue and 418 Beverly Avenue Monday, July 8 to Friday, July 12 from 7:00 a.m. to 5:00 p.m. Traffic will be allowed through as needed but vehicular traffic is advised to avoid the area Read On...